Ouko queries spending on key Mandera projects since 2013

Mandera Governor Ali Roba whose administration initiated heavy capital development projects since 2013. Auditor-General Edward Ouko has questioned the County’s development expenditure since 2013. PHOTO | FILE | NATION MEDIA GROUP

What you need to know:

  • Governor Ali Roba’s administration initiated heavy capital development projects including the county headquarters.
  • Two contractors were given a tender to upgrade Mandera town road to bitumen standards at a cost of Sh2.4 billion in 2014.
  • The county headquarters contract was re-awarded to Bima Investment Limited on March 5, 2018 at a cost of Sh455 million.

Auditor-General Edward Ouko has questioned the Mandera County executive’s development expenditure since 2013 in an audit of 2017/2018 financial year.

Mr Ouko questioned the motive and means used by the county executive in cancelling and re-awarding tenders for heavy capital projects since 2013.

On the advent of devolution, Governor Ali Roba’s administration initiated heavy capital development projects including the county headquarters, a new county assembly block, a county rest house and the governor’s residence among others but none has been completed to date.

TOWN ROAD

Two contractors were given a tender to upgrade Mandera town road to bitumen standards at a cost of Sh2.4 billion in 2014.

Mr Ouko’s report indicated that the Mandera executive entered into an agreement with Frontier Engineering Company Limited on July 1, 2014 and the contract for road tarmacking was to expire at June 30, 2016. But it was extended to April 30, 2018 under unclear circumstances.

“Again the same contract was extended to April 2019 but records [provided] for audit review showed some sections of the road were yet to be completed,” said Mr Ouko.

Lafey Construction Company Limited was contracted to do another lot of the same road at a cost of Sh1.2 billion on July 1, 2014.

Both companies had been paid at least Sh2 billion by November 2018 according the report.

Mr Ouko said the propriety of Sh2.4 billion for the 24-kilometre road could not be confirmed.

COUNTY HEADQUARTERS

On April 2, 2014, Sh290 million was awarded to Green County Construction Company Limited to build the county headquarters.

The contractor was expected to finish the project by October 30, 2015 but on December 18, 2017, the county chief officer for Public Works and Roads terminated the contract. He cited non-performance by the contractor.

Valuation of works on the project was done by Odesey International Limited, a consultant manning the project.

Mr Ouko observed that the county executive failed to engage a government registered valuer to carry out valuation of the project but instead engaged Odessey International Limited whose mandate was to man and act as a project management consultant.

“The executive failed to establish the value of outstanding works in monetary terms,” he concluded.

RE-AWARDED

The county headquarters contract was re-awarded to Bima Investment Limited on March 5, 2018 at a cost of Sh455 million.

Tender documents for the new contract were not provided for audit review but physical verification of the project showed on October 24, 2018 that the contractor was on site and the project was ongoing.

Mr Ouko concluded that in view of the anomalies, the authenticity of the total contract sum of Sh623 million could not be confirmed.

The probity of another contract worthy Sh602 million could also not be confirmed.

COUNTY REST HOUSE

The county rest house contracted at Sh294 million to Diwafa Investment Company Limited on April 2, 2014 was also terminated.

Mohamed Mohamud and Sons Construction Company Limited was re-awarded the same contract at Sh309 million. The project’s progress report and the breakdown of the amount paid to the first contractor was not produced for audit.

Another Sh33 million for a water supply project at Shafshafey and Kamor areas was also lost, according to Mr Ouko.

He accused the county of failing to produce tender opening minutes and tender opening register for Elwak small and medium enterprise market costing Sh327million.

IDP HOUSING

Tendering for Rhamu IDP housing project phase two was also questioned.

It was established that bidders were required to submit a minimum bid security of Sh400,000 whereas tender advertisement in a local daily prescribed a minimum bid of Sh200,000.

Stalled projects as per the report include the governor’s residence at Sh107 million, county assembly block at Sh185 million, regional livestock market at Sh170 million and Rhamu water supply project at Sh22 million.

Mr Ouko reported that the executive also failed to save most projects from depletion nor to add value on the investment of public funds.

Mr Ouko questioned how the tendering for Falama water project in Mandera South worth Sh212million was done.

“It is not possible to ascertain the total number of tenderers who applied in each category of projects procured,” he said.

The Falama project was initiated in the 2016/2017 financial year and is set to be launched this April.

FINANCIAL RECORDS

Mandera recorded qualified opinions from the auditor in 2017/2018 and 2016/2017 financial years. This means the county failed to present its financial records in accordance with accounting practice.

In the 2015/2016 and 2014/2015 the county managed adverse opinion, meaning there was a gross misstatement and, possibly, fraud in preparing county financial records.

In 2013/2014 a disclaimer opinion was rendered, meaning Mandera lacked a proper maintenance of financial records.

The auditor-general’s report states that the county has employed staff with questionable academic qualifications.

Orthopaedic trauma technicians, revenue collectors, watchmen, dental technologists and registered clinical officers are among county staff with questionable academic credentials.