County, contractor trade blames over stalled Dandora road project

City Hall, Nairobi County headquarters. The county government is on the spot for spending Sh250m for the rehabilitation of John Osogo Road in Dandora which remains unfinished. PHOTO | FILE | NATION MEDIA GROUP

What you need to know:

  • The construction of the road has seen four extensions with the latest one lapsing on September, 2019.
  • The contractor accused City Hall of violating its contract in terms of payment.
  • Nairobi Environment Executive said the contractor has been paid Sh70 million out of the Sh171 million contract sum.
  • The Finance department maintain that no payments will be done until the work on the road is 100 percent done.

City Hall is once again on the spot over a stalled road project which has taken more than three years to be completed despite millions pumped into its construction.

Blame games between the county government and the contractor responsible for the rehabilitation of John Osogo Road in Dandora Phase 4 continue even as the road lies in pathetic condition.

The main road leading to Dandora Dumpsite, has gobbled up millions in budgetary allocations since the days of the defunct Nairobi City Council.

In 2016, the former regime of Governor Evans Kidero set aside Sh180 million towards its repair and since then the construction of the road has seen four extensions with the latest one lapsing on September, 2019.

The area MCA Francis Otieno has complained of the contractor missing from the site and that he resurfaced only to do 100 metres of the road before disappearing again.

DELAYED PAY

Nairobi Environment Executive Vesca Kangogo said the contractor – Nyoro Construction Company – has been paid Sh70 million out of the Sh171 million contract sum but the contractor has delayed work demanding interest on payments invoices not paid within 28 days.

“This is not feasible because our budgets do not have provisions for interest on delayed payments. All payment certificates have been paid but the contractor has refused to go back to site."

“However, we are considering other venues to compel the contractor to complete the work or make a decision on how the road can be completed without further delay and within the budget,” added Ms Kangogo while appearing before Nairobi County Assembly Environment Committee.

However, the contractor accused City Hall of violating its contract in terms of payment while also saying that they are yet to be fully paid by the county.

“Our contract was for eight months and although some of the money has been paid, the balance has not been honoured. The county should pay the tender sum plus interests of one year if they want the road to be completed,” said Engineer Nyoro.

Admitting to the delay in payments, Director of Environment Isaac Muraya said the delays in the payments was occasioned by variations between the Environment and Finance Departments over when the money is to be paid.

The Finance department maintain that no payments will be done until the work on the road is 100 percent done.