Kenya, Japan to fund Nairobi overpass to decongest CBD

An impression of the proposed Nairobi overpass that will link Enterprise Road to Nairobi Central Business District in bid to reduce traffic in the city centre. PHOTO | COURTESY

What you need to know:

  • Project will be undertaken by Kenya Urban Roads Authority.
  • Kura acting boss Silas Kinoti said that the project was identified in the Nairobi Integrated Urban Development Master Plan 2030.

The government is set to construct an overpass to link Enterprise Road to Nairobi Central Business District.

The overpass also known as a viaduct — a long bridge-like structure, typically a series of arches, carrying a road or railway across a valley or other low ground— will fly over the railway yard at the Nairobi Central Railway Station.

The project is a collaboration between Kenya and Japan International Co-operation Agency (JICA) and will be undertaken by Kenya Urban Roads Authority (Kura), who are the implementing agency.

2030 MASTER PLAN

Kura acting director general Silas Kinoti, in a statement, said that the project was identified in the Nairobi Integrated Urban Development Master Plan 2030 as a priority project to reduce traffic congestion within city centre and divert traffic from Mombasa Road.

“At the same time it is intended to go a long way in expanding the CBD as well as alter permanently the Nairobi city centre landscape and give it a modern look,” said Mr Kinoti on Tuesday.

Mr Kinoti said several studies have been conducted in compliance with relevant Kenyan laws and JICA environmental and social safeguard guidelines.

RELOCATIONS

He said feasibility studies, environmental and social impact assessment and ongoing resettlement action plan (RAP) are being conducted by a JICA commissioned study team

“So far, several consultative meetings …have been held with stakeholders including the Muthurwa Estate residents as part of the ongoing RAP process,” he said.

The Kura boss said, according to feasibility studies conducted in 2016, a section of the viaduct would be constructed on land currently occupied by Wakulima market but several other options have been identified to ensure traders are not disenfranchised during the construction period.

 He said Muthurwa Estate was identified as an alternative site for relocation of the market during consultations with various stakeholders including representatives of the Wakulima market traders, Nairobi City County government, Kenya Railways Staff Retirement Benefits Scheme (KRSRBS) and Kura.

“The Project planning and study activities are part of an ongoing process that will give recommendations and inform stakeholders including the government of Kenya and JICA on the project’s viability,” he said.